Information | Calculate | |
---|---|---|
Basic Information | ♦ Address ♦ GPS Location ♦ Date ♦ Project Durations | (Google Map) (Longitude, Latitude) (Month/Day/Year) (hours) |
Direct Cost |
♦ Emergency Response Costs![]() ![]() ![]() ![]() ![]() ![]() |
$
Fire Dept. $
Duration: hours
Vehicle Number: * 81.4$/vehicle from Fire Dept.
Labor-Captain Number:*35$/Captain
Labor-Operator Number:*31$/Operator
Labor-Firefighter Number:*24$/Firefighter
Ambulance $
Duration: hours
Vehicle Number: * 40.5$/Amublance
Labor-Driver Number:*11$/Driver
Labor-Paramedics Number:*17.52$/Paramedics
Police Dept. $
Duration: hours
Vehicle Number: * 15.69$/vehicle from Police Dept.
Labor-Officer/Chiefs/Leutenants Number:*21.4$/Person
Other Emergency Responder Cost $
Duration: hours
Prosecutors Office/Arson Unit/etc. Number:*$/Person
$ Calculator
$ Calculator(Recommend Value: 262$/hour * project duration)
$ (Recommend Value: 450$)
$ (Recommend Value: 1000$ -12000$)
$
$
![]() |
Indirect Cost |
♦ Loss of Income ![]() ![]() ![]() ![]() ![]() ![]() ![]() |
$
$
Pavement Service Life Reduction=(m) × 110 ($/m)
(Excavation lengh) ×(Estimate decrease in road surface value)
$![]()
Loss of Parking Meter $ (Recommend Value: 91-239$/day)
=(Num)*
($/g)*
(%)* Project Duration(h)
(Parking Space Number)*(Meter Rate)*(Occupancy Frequency)*(Duration)
Loss of Parking Fine $
=($)*
(Frequency)* Project Duration(h)
(Ticketing fee)*(Frequency of Ticketing)*(Duration)
$
$
$
$
|
Social Cost |
♦ Costs to Highway Users ![]() ![]() ![]() ![]() |
$
Traffic Delay Cost
$ (Recommend Value: 45$/day -8477 as max)
DT=
(km)/
(km/h) -
(km)/
(km/h)
DT(Delay Time(h)) = (Length of work zone including detours)/(Speed through work zone - (Length of working zone in normal situation)/(Normal speed)
CD=
DT(Delay Time(h))*
($/person/h)*
(person/vehicle)
CD(Cost of Delay per vehicle)=(Delay time)*(Value of Time)*(Average Person Num per Vehicle)
TDC=
CD(Cost of Delay per vehicle)*
(vehicle/day)*
(days)
TCD(Total Traffic Delay Costs)=(Cost of Delay per vehicle)*(Vehicle Num per day)*(Projection duration by day)
Increased Vehicular Operating Costs
$ (Recommend Value:29$/day -2581$/day)
=
(km)*
($/km-vehicle)*
(Num/h)*Project Duration(h)
(Increased Travel Distance)*(Operating Cost Allowance)*(Number of vehicles/hour)*(Duration)
Loss of Pedestrain Travel Time
$
=
($/h)*
(num)*
(h/person)* Project Duration(h))
(Value of Time)*(Number of Pedestrians)*(Increased Travel Time)*(Duration)
Increased Collision Rate $
=
($/km)*
(km)
(Num/day)* Project Duration(day)
(Avg Cost of Collisions)*(Route length)*(AADT-Number of Vehicels/day)*(Project duration by day)
$
Property Damage $
Loss of Business $ (Recommend Value:433$/day -2624$/day)
=(Num)*
($/unit/day)*Project Duration(h)*
(%)
(Num of affected business unites)*(Average daily incomme of business unit)*(Duration)*(Percentage of business loss during construction)
$
Cost of Noise Pollution
$ (Recommend noise cost: 8$/day)
=
(num)*(project duration)* (
($/h) -
($/h))
(Number of affected inhabitans)*(Project duration in days)*{(Noise cost value during construction work)-(Nose cost value pre-constructionn situation)}
Air Pollution
$
=
($/metric ton) *
(metric tons)
(Volumetric emission cost)*(emmitted volume)
Cost of Dust Pollution
$ (Recommend Value:61$/day -149$/day)
=
(h/week)*
($/h)*(Duration in Weeks)
(Additional cleaning times)*(Wage)*(Duration in Weeks)
$
|
Add Notes | Please add your notes here |
Edit Cost Indicators and Click Caculate Total Cost Button to get the estimated total cost of the project. Click generate Excel button to download the total cost report in csv version.
Our computer analysis tool can be used to determine the impact on the community and total cost of excavation damages. In our project, excavation damage cases will be analyzed to determine the impact on the community (interruption of utility services, property damage, traffic impact, disruption of residents and businesses, etc.) and the total costs for repairs, restoration of services, use of police, fire, and other local responders, associated underground utility response costs, financial impact on businesses, etc. The project will provide a means to measure the total impact of excavation damage cases and to develop a range of civil penalties that reflect the severity of the excavation damage on the community.
Load More