Utility Strikes Cost Catalog | |
Direct Cost | |
Administrative Cost | |
Occupation | Labor Rates ($/h) |
Sr. Engineer | 74 |
Manager | 61 |
Project Engineer | 56 |
Operator | 30 |
Compliance Officer | 41 |
Lawyers | 76 |
Contracted Compliance Personnel | 225 |
Planning and Designing | |
Yet to receive | |
Diversion of Existing Utility Services | |
Location Type | Charges ($) |
Commercial | 450 |
Residence | 450 |
Construction Costs - Repair Costs | |
Material Diameter | Charges ($/5') |
12" pipe | 41,600 |
24" pipe | 62,400 |
36" pipe | 93,600 |
Traffic Management | |
Work time | Lane Closure Fee |
Weekday (9:00AM - 3:00PM) | $6000/day |
Weekday (6:00PM - 6:00AM) | $1000/day |
Weekends (6:00AM - 6:00PM) | $10,000 |
Weekends (6:00AM - 6:00PM) (Detour) | $50,000 |
Traffic Management (Traffic Control Device Cost) | |
Yet to receive | |
Emergency Cost | |
Type of Emergency Service | Charge/hour |
Fire Personnel - Captain | 35 |
Fire Personnel - Operator | 31 |
Fire Personnel - Fire fighter | 24 |
Fire Truck (100ft Ladder) | 100 |
Fire Truck 1000 GPM | 68 |
Fire Truck `1250 GPM | 72.25 |
Fire Truck 1500 GPM | 78.9 |
Fire Truck 2000 GPM | 81.4 |
Fire Truck (75FT) | 117.1 |
Fire Truck (150FT) | 142.75 |
Fire Truck (Rescure Equipment) | 93.47 |
Ambulance Attendee - Paramedics | 17.52 |
Ambulance Driver | 10 |
Ambulance - 150 | 28 |
Ambulance - 210 | 40.5 |
Police Wage | 21.4 |
Police Automobile | 15.69 |
Restoration Costs | |
Yet to receive | |
Inirect Cost | |
Regulatory Fines | |
Min. ($) | Max. ($) |
25,000 | 19,200,000 |
Average | 5,782,857.14 |
Interruption of Services | |
Yet to receive | |
Loss of Income (Local businesses) | |
Yet to receive | |
Costs to Highway Authority (Pavement Service Life Reduction) | |
Average estimate of service life reduction | 110 $/m |
Damage of Third Party Apparatus | |
Min. ($) | Max. ($) |
400,000 | 700,000 |
Average | 550,000.00 |
Compensation Payements | |
Yet to receive | |
Loss of Parking Revenues | |
Meter Rate ($/h) | 1 |
Occupancy Frequency (%) | 0.6 |
Social Cost | |
Noise Pollution | |
Reduction Percentage of Property due to Noise | 0.55% |
Air Pollution | |
Yet to receive | |
Dust and Dirt | |
Min. ($)/day | Max. ($)/day |
61 | 149 |
Lost Business Income | |
Min. ($)/day | Max. ($)/day |
433 | 2624 |
Increased Vehicular Collision | |
Min. ($)/day | Max. ($)/day |
29 | 2581 |
Traffic Delay Cost | |
Min. ($)/day | Max. ($)/day |
45 | 8477 |
Property Damage | |
Min. ($) | Max. ($) |
0 | 8477 |
Average | 1,500,000.00 |